On the morning of July 19, 2019, DINCO E&C and Sunshine Aerospace Aviation Components Plant Project were pleased to welcome the visit of Danang leaders. Members of the delegation include:

– Mr. Truong Quang Nghia – Member of the Party Central Committee, Secretary of the City Party Committee;

– Mr. Huynh Duc Tho – Standing Member, Deputy Secretary of City Party Committee, Chairman of City People’s Committee;

– Mr. Nguyen Nho Trung – Member of Standing Board of City Party Committee, Chairman of City People’s Council;

– Representative leaders of Office of City Party Committee, Office of National Assembly Delegation, City People’s Council and City People’s Committee;

– Together with representatives of Da Nang city departments.

During the tour, DINCO E&C reported to the leaders about the miraculous construction progress of the project. With only 30% of construction time, DINCO E&C team completed more than 50% of the total project output.

Leveling and fencing items exceed 4 months ahead of schedule; item of main factory foundation is 2 weeks ahead of schedule; infrastructure item including manholes, drainage culverts, slopes is 2 months ahead of schedule. Other items are being executed on schedule, no delay items.

The main factory is expected to be completed on August 15, 2019 and handed over to the Owner for installation of the machines; the whole project will be completed and handed over to put into use on December 31, 2019.

At the meeting, the leaders highly appreciated and congratulated DINCO E&C contractor on the construction progress of Sunshine Aerospace Aviation Component Manufacturing Plant Project which exceeds the Owner’s expectations with outstanding construction quality.

 